Secure lot to determine plan
|
4 weeks
|
Draft plans for bidding and building
- Foundation
- Walls
- Windows
- Flooring
- Cabinets
- Shingles
- Brick
- Cabinets
- Color/type of plumbing fixtures
- Amenities
- Trim exterior and interior
|
|
Secure contracts, financing and close on lot
|
3 weeks
|
Order windows/doors
|
4 weeks
|
Obtain building permits
|
|
Install foundation
|
2 weeks
|
Build rough frame house
|
4 weeks
|
Pick out siding/brick and shingles
|
|
Mark out for electrical/walk thru for framing changes
|
3 weeks
|
Determine cabinet layout and order cabinets
|
|
Rough plumbing, electrical, heating and insulation
|
|
Drywall
|
3 weeks
|
Pick out light fixtures
|
|
Determine type of interior trim/doors order
|
|
Paint walls and interior trim finish
|
4 weeks
|
Determine type of floors and where they will be
|
|
Order countertops
|
|
Order carpeting
|
|
Pick out garage door
|
|
Install flooring, countertops and detail
|
3 weeks
|
Finish all trades
|
|
Install the driveway
|
|
Complete Yard, landscaping, sprinkler system
|
|
Detail and finish
|
2 weeks
|