You want to build a custom home, but where do you start? You may say to yourself, “There are so many things to consider I already feel behind, and how much is all of this going to cost?” Building is a big step but our clean sequential building process can make the experience fun and rewarding for you and your family. Let’s take a look.​

PRIOR TO BUILD:
Initial Contact
DURATION:
2 – 8 weeks*
INVESTMENT:
Complimentary
There is no one starting point to creating a home. Whether you already have a lot and a vision for your home, or are just beginning to think about building, we meet you where you are. In our Welcome Package we focus on three primary components.
FIRST: Vision. We want to understand your vision, your ‘true north’ of the project which can be achieved through a few emails and phone calls.
SECOND: Property. If you have a lot we will schedule a site visit to determine project feasibility. If you do not yet have a lot, we can assist you with finding that perfect spot.
THIRD: Budget. Based off discussions and site visits (if applicable) up to this point, we will then provide a proposed budget trajectory. We work closely with our clients to ensure that the scope of the project and the budget are comfortably in reach and aligned to the vision. If the decision is made to move forward, we have preferred financial lenders that offer competitive financial products and rates.

PRIOR TO BUILD:
Designing Your Home
DURATION:
8 – 16 weeks*
INVESTMENT:
Per Project from $3499
Now the fun begins! In this step we will ask you to share three primary types of information with us so that we can begin to layer and organize the project.
Photos: Pinterest boards, Houzz idea books, magazine photos, etc.
Floor Plans: we would like to see anything that you find interesting.
Desires: a list of “must have, want to have, need to have, and do not want” helps us confirm that the drawing set includes only what is important and desired by you.

PRIOR TO BUILD:
Purchasing a Lot
DURATION:
4 – 12 weeks*
INVESTMENT:
Lot Specific
There are several important considerations when purchasing a piece of property. One of the most important is “Will my project work with this lot?” It’s a great question, which is why we work so hard to gain clarity on the details of the home before a property is purchased, or developing existing property. Additionally; elevation, zoning, and available utilities are all important considerations. Once these items have addressed we can discuss the setting of the home and driveway, the interior and exterior sight lines and axial orientation.

PRIOR TO BUILD:
Site Preparation
DURATION:
4 – 12 weeks*
INVESTMENT:
From $2800
During site preparation the home, auxiliary buildings, driveway, utilities, geo-loop, well & septic are laid out for review and approval.

Lending & Contract
Documents
DURATION:
4 – 6 weeks*
INVESTMENT:
From $249,000. Detailed in Contract
We will work with the client to finalize the drawing set, building specifications, and a contract to submit to the lender for project approval and funding.

THE BUILD:
The Foundation
DURATION:
4 – 8 weeks*
INVESTMENT:
Detailed in Contract
The foundation is the beginning of the actual build. Dimensions and related details are built to spec and your project begins to come out of the ground. During this phase, the excavation, ICF foundation, waterproofing, under slab plumbing and concrete slab work will all be completed.

THE BUILD:
Under Roof
DURATION:
8 – 16 weeks*
INVESTMENT:
Detailed in Contract
From the foundation, we begin building the walls of the main floor and above. Upon completion of the “under roof” phase, your project will be completely framed with doors and windows installed and the roof will be weatherized.

Mechanical, Electrical & Plumbing (MEPs)
DURATION:
4 – 6 weeks*
INVESTMENT:
Detailed in Contract
In this phase the mechanical trades such as HVAC, electrical and plumbing begin. The drawing set and specs provide the layout for the kitchen and bathroom areas, and all piping, wiring and associated items that need to be mounted in the wall cavities are roughed-in. Upon completion of MEP’s the project is inspected and staged for the insulation and drywall packages.

THE BUILD:
Insulation, Inspections, Drywall & Exterior Finishes
DURATION:
5 – 7 weeks*
INVESTMENT:
Detailed in Contract
During this phase, the project really begins to take shape. The spray foam is applied in all contracted spaces, from the roof deck to soundproofing walls. An inspection is ordered to be granted approval to cover all exposed mechanicals. Now the drywall can be installed, and the project becomes a 3-D space. On the exterior, the trim, siding and brick or stone is applied. All the rooms, angles and turns come to life.

THE BUILD:
Paint, Flooring, Interior Trim, Cabinets & Tops
DURATION:
6 – 8 weeks*
INVESTMENT:
Detailed in Contract
Color, texture and function define this phase. We are now into the finishes of the project. Color will be applied to the walls, flooring and cabinets are installed. This is a fun phase as you get to see for the first time your selections fill the space.

THE BUILD:
Fixtures & Appliances
DURATION:
2 – 4 weeks*
INVESTMENT:
Detailed in Contract
At this phase the home is nearly complete. After the fixtures are set and the appliances are installed, they are tested for quality assurance and functional performance. You can even ring your own doorbell!

THE BUILD:
Punch Out & Closing
DURATION:
2 – 4 weeks*
INVESTMENT:
Detailed in Contract
The house is now complete. During punch out, we walk through the project top to bottom making sure all items are in place. Once that is complete there is a final clean that puts a sparkle on every item. Following the final clean, we will do a final walkthrough of the project with the client.
​
Welcome to Your New Home!

POST-BUILD:
Warranty
DURATION:
12 Months
INVESTMENT:
Detailed in Contract
We are committed to building a home that meets client expectation. Within the first 12 months following completion of the build we will address most cosmetic items. Appliances and fixtures are covered through manufacturers’ warranties. To further protect your investment, extended service agreements are available with several of our vendors, keeping your home operational and maintained.

DISCLAIMER:
Estimated construction timelines are approximate and subject to change based on factors like weather conditions, permit approvals, material availability, and unforeseen circumstances, etc. Crane Builders cannot guarantee a specific completion date, and any provided timeframe should be considered a guideline only.